icon

Project

Overhaul of the Thermal Power Plant

icon

Industry

Energy Facilities

icon

Year

2020 - 2022

icon

Duration

Three years

icon

The value of the project in 2022

750.000

icon

The value of the project in 2021

350.000

icon

The value of the project in 2020

1.100.000

Customer/Client

Thermal Power Plant Stanari

Description

Installation of evaporation panels on the water walls of the combustion chamber (2022)

Installation of evaporation panels on the outer water wall of the combustion chamber (2021)

Installation of evaporation panels on the water walls of the combustion chamber (2020)