Overhaul of the facility M&TPP Ugljevik
- Home
- Projects
- M&TPP UGLJEVIK
- Overhaul of the facility M&TPP Ugljevik
Project
Overhaul of the facility
Industry
Energy Facilities
Year
2022 - 2023
Duration
Two years
The value of the project in 2023
586.246
The value of the project in 2022
1.031.519
Customer/Client
Mine and Thermal Power plant Ugljevik
Description
Overhaul in 2023 - from May 16th until June 23rd 2023.
- Replacement of part of the piping system of the combustion chamber
- Overhaul of coal powder channel and burner
- Overhaul of the mill plant
- Mechanical maintenance of boiler equipment during overhaul
- Construction of pipe bypasses
- Replacement of the damaged part of the steam pipe system
- Thermal treatment of welded joints during overhaul
Overhaul in 2022 - from September the 9th until November the 1st 2022.
- Replacement of part of the piping system of the combustion chamber
- Overhaul of coal powder channel and burner
- Overhaul of the mill plant with torquetting of channels and mill doors
- Mechanical maintenance of boiler equipment during overhaul
- Construction of pipe bypasses
- Overhaul of reinforcement
- Thermal treatment of welded joints during overhaul
- Reparation of convective steam reheaters CSRP1 and CSRP2
- Replacement of pipe hangers and pipes on the steam superheater panels