Overhaul of the Clean petroleum fuel terminal
- Home
- Projects
- OTF SARAJEVO
- Overhaul of the Clean petroleum fuel terminal
Project
Total overhaul of the Clean Petroleum Fuel Terminal Blažuj
Industry
Refinery and Petrochemical
Year
2022 - 2023
Duration
547 days
The value of the project
10.396.230
Customer/Client
OTF Ltd. Sarajevo
Description
Total overhaul of the Clean petroleum fuel terminal Blažuj
Mechanical works:
- Uninstallation and installation of pipelines, reinforcement, shaped pieces and support pieces
- Installation of metal sheets for a double floor, dome roof, floating roof, aluminum dome roof, connections, measuring strips for tanks T1, T2, T3, T4, T5 and T6
- Procurement and installation of equipment (pumps, deaerator, insertion arms, VRU units)
Construction works:
- Preparatory works, the upper layer of the platform, concrete reinforcement works on the space frame construction, transitions, platforms, supports for pipelines and frames, shafts
- Installation of gutters on the filling station structure
- Renovation of the covers on the wagon platform