Installation of mechanical equipment for the transportation system
- Home
- Projects
- RUDIS TRBOVLJE
- Installation of mechanical equipment for the transportation system
Project
Installation of mechanical equipment for the transportation system
Industry
Energy Facilities
Year
2020
Duration
273 Days
The value of the project
631.521
Customer/Client
Rudis Ltd. Trbovlje
Description
Installation of mechanical equipment for the transportation system
- Placing the pontoon platform on the route
- Installation of leading and returning rolls on pontoons
- Installation of tension and operating drums
- Installation of the upper and lower line routers
- Installation of line scratchers and wipers
- Installation of line units and hoppers
- Installation of the hood
- Pulling in the tape onto conveyors and vulcanization of the tape
- Installation of operating, returnable and tensionable units