Installation of hot pipeline gas boiler with following equipment and burner
- Home
- Projects
- MODRIČA OIL REFINERY
- Installation of hot pipeline gas boiler with following equipment and burner
Project
Installation of hot pipeline gas boiler with following equipment and burner
Industry
Refinery and petrochemicals
Year
2021
Duration
71 day
The value of the project
175.755
Customer/Client
Modriča Oil Refinery
Description
Delivery and installation of hot pipeline gas boiler with following equipment and burner
- Delivery of Viessmann gas boiler 1600 KW, with following equipment, and Weishaupt burner WM - G20/4-A
- Delivery and installation of a two-layer stainless steel funnel with thermal insulation between the stainless steel layers
Construction of a gas boiler house and platform with trailers
- Architectural and construction works
- Water supply and sewerage installations
- Outdoor installations
- Electrical installations
- Machine installations
- Construction works
- Electrical works
- Mechanical works