Project
Disassemble and assemble of steam pipelines - TPP Tuzla
Industry
Energy Facilities
Year
2023
Duration
94 days
The value of the project
1.353.441
Customer/Client
Dongfang Electric International Corporation
Description
Reconstruction of the boiler in The Unit 6 - TPP Tuzla
- Replacement of the main pipeline for fresh steam, including the installation of hanging brackets, drainage, venting and impulse lines up to the first partition valve
- Replacement of intake reducing stations RS-1 and RS-2 and equipment for RS-3
- Replacement of flowmeters in the main pipe and connection lines of fresh steam