Replacement of a new inlet hood, inlet pipeline system with compensator and thermal insulation
Project
Replacement of a new inlet hood, inlet pipeline system with compensator and thermal insulation
Industry
Metallurgical Facilities
Year
2020
Duration
106 days
The value of the project
522.114
Customer/Client
ArcelorMittal, Zenica
Description
Agglomeration - AMZ
Replacement of a new inlet hood, inlet pipeline with compensator and thermal insulation, rehabilitation of the outlet hood, replacement of the outlet pipeline, rehabilitation of the air tunnel above the bypass and collecting baskets on HF 5.